Lake Zwerner Pedestrian Bridge in Dahlonega: Fall 2026 Status

At Lake Zwerner, which is the City of Dahlonega's name for the Yahoola Creek Reservoir, three changes are due within a few weeks of each other. The pedestrian crossing that completes the loop trail, the rebuilt boat ramp picnic area, and the reopening of a restricted stretch of shoreline are separate projects with separate contracts. Their schedules are tied together. The picnic area work is timed to match the bridge, and the shoreline restriction exists because of bridge construction. If you walk, paddle or fish at Zwerner, the reservoir you use this fall is still running on its temporary setup, and the permanent version should arrive all at once.

The Gap on Highway 9

The reservoir was built between 1999 and 2003. Its perimeter trail runs about 3.2 miles and is maintained by Lumpkin County, according to the city's Lake Zwerner facility page. The loop has one weak point. To get from one end of the trail to the other, walkers have had to use the existing highway bridge on Morrison Moore Parkway, which is Highway 9 North.

The city's Morrison Moore Pedestrian Bridge & Sidewalk project removes that crossing. The Dahlonega Nugget reported that the bridge is designed to connect the two ends of the reservoir trail loop away from the highway bridge. The project also adds a sidewalk from the Walmart parking lot to the new bridge. Once it's open, the loop no longer depends on the highway shoulder, and a new walking route comes in from the shopping side of Morrison Moore Parkway.

The project has been in the works since 2018. In an earlier Nugget report, council chose Strickland & Sons as the contractor at its last meeting of the year, based on a low bid of $4.95 million. In May 2025 the Nugget reported that GDOT would cover 80% of construction costs up to $4.95 million. The other 20% is a local match, mostly from the city with some county money. The draft dedication plaque the city prepared this spring lists three funding sources: TSPLOST, GDOT's Transportation Alternatives Program, and Lumpkin County. That makes it mostly state and federal transportation money, plus local sales-tax dollars, spent on a pedestrian crossing at a city reservoir.

Where the Bridge Stands in October

Heavy construction started this year. The city's February 2026 Public Works report expected bridge pieces to start arriving the week of March 12. A Nugget report from March described contractors putting the bridge sections together on site.

On April 23, city staff sent council a memo proposing a bronze plaque for the project, installed "at the time of dedication/opening." Council took it up at its May 4 meeting. That plaque is a planned item. It doesn't mean the opening has happened.

The most recent city Public Works report, for July 2026, still lists "Morrison Moore Pedestrian Bridge & Sidewalk" as ongoing. The Nugget's 2025 forecast had the work finishing in late 2026. As of mid-October, the city hasn't announced an opening date or a dedication. Until it does, plan on the current route along Morrison Moore Parkway.

Three Projects on Overlapping Timelines

The bridge would be news on its own. It matters more because two other reservoir projects are set to follow it.

Project What it affects Latest public status Timing or cost marker
Morrison Moore Pedestrian Bridge & Sidewalk The trail gap at Highway 9 North, plus the sidewalk from the Walmart lot Listed as ongoing in the July 2026 Public Works report Forecast for late 2026
Boat Ramp Picnic Area beautification The picnic area beside the boat ramp Contract award to Hasbun Construction LLC on the September 21, 2026 work-session agenda Not to exceed $175,842.98
Partial boat traffic and shoreline restriction One section of the lake near construction City notice set it at "roughly 18 months" Began July 7, 2025, which points to about January 2027

The picnic area is the clearest case. In its February 2026 Public Works report, the city put Boat Ramp Picnic Area beautification on its upcoming list and timed the work to coincide with the bridge's completion. The project then went through bidding over the summer. The city's purchasing page posted a bid tabulation dated August 28, 2026. The September 21 work-session agenda included "Approval to award Contract for the Boat Ramp Beautification Project (Project Number: 2026-005) to Hasbun Construction LLC in the not to exceed amount of $175,842.98," presented by City Engineer Mark Buchanan. The bridge is a $4.95 million job. The picnic area work is a much smaller project, and it's intended to finish the part of the reservoir that most visitors see when they arrive.

The shoreline restriction is the third piece, and it comes directly from the bridge work. In a June 24, 2025 notice, the city said a section of the lake would be closed to boat traffic and shoreline recreation starting July 7 and "lasting roughly 18 months." Eighteen months from July 7, 2025 is about January 2027. The city described that period as approximate, and it hasn't posted a notice ending the restriction.

So the dates line up. The bridge's late-2026 target, the picnic area work timed to match it, and the shoreline restriction's estimated end all fall within a few weeks of the new year. Once those are done, Zwerner should have a complete loop, a rebuilt picnic area at the ramp, and the restricted shoreline back in use.

What Stays Open While the Work Finishes

The reservoir hasn't been closed during construction. The city reopened the boat ramp and parking area on August 7, 2025 and warned there could be shorter closures from time to time while work continued. For an October paddle or a weekday walk, that means:

  • The ramp and its parking area are open, though short closures are still possible while the bridge and picnic area work wraps up.
  • The section covered by the July 2025 notice remains off-limits to boats and shoreline recreation until the city says otherwise.
  • The loop is still 3.2 miles with the Highway 9 North crossing in it. Until the city announces the bridge is open, the walk works as it always has.

The Rules on the Water

The reservoir plan included in the city's May 2026 council packet sets out the following, and none of it is tied to the construction:

  1. Boating is human-powered: canoes, kayaks, stand-up paddleboards and sculling. Public boats with gasoline or diesel motors aren't allowed.
  2. Boats may launch only from designated sites. Those launches close when the reservoir level is at or below 1,232 feet above mean sea level.
  3. Fishing is allowed only in designated areas and seasons, and anyone not exempt needs a valid Georgia fishing license year-round.
  4. Fishing from public roads and bridges is prohibited.

The water-level rule is the one most likely to catch someone off guard. Zwerner is a working water supply, so a dry stretch can close the launches even when the ramp, the parking lot and the weather all look fine. The facility page also notes that fishing is limited to city-designated areas and hours. If you plan to fish near the new crossing once it opens, read the bridge prohibition above and check with the city first. This summary is general information. Confirm current rules, licensing and any exemptions with the City of Dahlonega or Georgia DNR before you go.

The Signals to Watch

The city's own reports and notices are where the opening will be announced. A Public Works report could move the bridge out of the ongoing list. A dedication date could be announced, with the bronze plaque council discussed in May. A notice could lift the shoreline restriction. The city's news page and its department reports archive are where those updates are posted. The archive currently runs through the July report. The next reports are where the bridge's status will change. The Hasbun contract, if approved, is the next thing to look for at the boat ramp.

Until then, the familiar route along Morrison Moore Parkway is still the way around the loop. Around the new year, the city's targets have the trail, the ramp area and the shoreline all changing within a few weeks of each other.

Long-planned public projects like this one change what a part of town is like to live near. Knowing where projects such as the Morrison Moore bridge stand is part of reading the town as a resident. If you'd like to talk about how projects near Lake Zwerner and across Dahlonega fit with your plans, Lucia Brooks - Towe is glad to share what she's following. Let's Connect.